| NL's AG finds "issues" with Fisheries Department |
|
The Newfoundland Auditor General, John Noseworthy, presented his 2009 report to the Government on January 28. Among other areas, he revealed several issues with the administration of one particular program in the Department of Fisheries and Aquaculture.
There was no suggestion of wrong-doing rather, questionable management practices.
Below is the actual section from the report:
The Department of Fisheries and Aquaculture administers the Fisheries Technology and New Opportunities Program (FTNOP). This is a $6 million program over the three fiscal
years 2008, 2009 and 2010. As at 31 March 2009, a total of $2.60 million had been approved for 63 projects.
The primary objective of the FTNOP is to fund eligible activities related to harvesting, processing, and marketing initiatives to diversify and increase the overall viability of the Provincial seafood industry. Its focus is to fund research and development in the
harvesting and processing sectors.
Our review indicated a number of concerns related to how the
Department is administering the FTNOP. We found that project
applications were not always assessed and approved in accordance
with program criteria, payments were sometimes made without the
required documentation and approvals, and projects were not always
adequately monitored to determine whether funds were spent as
intended. Furthermore, the Department did not establish measurable
criteria in order to determine whether the program objectives were
achieved. In particular:
Approval and Assessment
The approval and assessment process is required in order to ensure
that only eligible activities relating to the primary objectives of the
FTNOP are funded. We reviewed 40 approved projects and found a
number of weaknesses in the approval and assessment process as
follows:
10 projects totalling $444,248 the required application was not
on file to provide the required information necessary for a
proper assessment and to support either the approval or rejection
of the project. These projects were approved based on
proposals; however, the proposals did not contain all the
information and declarations as required in the application.
32 Auditor General of Newfoundland and Labrador
8 projects totalling $400,542 the application on file was
incomplete. For 2 of these projects, only the signed declaration
on the last page of the application was on file. Without a
complete application on file, it is questionable how a proper
assessment could be performed to support either the approval or
rejection of the project.
10 projects totalling $416,607 funding for overhead costs
totalling $68,416 was approved even though these expenditures
were not considered an eligible FTNOP cost as there was no
evidence on file to support that the overhead was directly a
result of the project. Existing overhead is not an eligible cost.
3 industry-related projects totalling $78,280 funding was
approved in excess of the FTNOP limits. The FTNOP has a
limit of 60% funding capped at $100,000 for industry-related
projects; however, in these cases, the total maximum funding
should have been $38,759 while $49,030 was paid, representing
76% funding.
36 projects totalling $2.17 million - Project Summary and
Approval Forms (PSAFs) on file were incomplete as follows:
22 projects totalling $1.11 million with 22 PSAFs - there
was no information to specify the eligible costs of the
project;
15 projects totalling $963,105 with 16 PSAFs - there was
no evidence that comments from the Department of
Fisheries and Aquaculture, the Department of Fisheries and
Oceans and other agencies were obtained as required;
11 projects totalling $772,537 with 11 PSAFs - there was
no evidence that comments from the Department of
Fisheries and Oceans were obtained as required;
12 projects totalling $879,375 with 12 PSAFs - there was
no evidence that comments from other agencies were
obtained as required; and
Auditor General of Newfoundland and Labrador 33
2 projects totalling $104,926 with 2 PSAFs - the required
signatures to document the approval were not on file.
16 projects totalling $808,518 - the required supplier quotations,
to support the estimated costs of the project, were not provided
with the application.
24 projects totalling $1.55 million - these projects were not
approved within the 45 days as outlined in the policy. The delay
in processing these 24 projects ranged from 1 day to 108 days in
excess of the 45 days.
The minutes of the Management Committee meetings did not
always document the decisions of the Committee relating to
projects. For 7 projects totalling $355,709 there was no
evidence in the minutes that the projects were recommended for
approval by the Committee.
Payments
Adequate documentation and support for eligible project costs are
required in order to ensure that payments are made in accordance
with policies and procedures. Our review indicated that the required
documentation to support payments was not always on file as
follows:
6 projects with payments totalling $249,476 there were no
supplier invoices on file to support that advance payments
totalling $212,122 were used within the required six month
timeframe.
16 projects with payments totalling $662,232 there were no
supplier invoices on file to support actual costs incurred
totalling $511,794. As a result, it was not possible to verify
whether the costs were accurate, actually incurred or if they
were incurred after the application date.
26 projects with payments totalling $1.20 million supplier
invoices to support actual costs incurred were not always signed
by the Project Officer to indicate that they were eligible costs.
34 Auditor General of Newfoundland and Labrador
4 projects with payments totalling $201,884 the required
payment memos were not always prepared.
30 projects with payments totalling $1.29 million the required
payment memos were prepared but incomplete.
Our review also identified errors totalling $44,747 in 7 projects as
follows:
$26,629 relates to payments for an industry-related project, in
excess of the 60% of eligible costs capped at $100,000.
Although maximum funding should have been 60% of $122,285
or $73,371, the actual funding was $100,000, $26,629 beyond
the maximum allowed.
$7,518 relates to payments for a project for management and
support costs that were not an eligible expense.
$1,805 relates to payments for a project for office supplies and
communications that were not an eligible expense.
6 projects (2 previous projects and 4 others) HST of $8,795
was funded although this expenditure would not normally be
funded. In 11 other projects there was insufficient
documentation on file to determine whether HST was funded.
Payments were not made in compliance with the terms of the
contract. For example:
2 projects final payments totalling $34,637 were made prior to
the receipt of the final report; and
1 project final payments totalling $1,908 were made prior to a
site visit.
Monitoring
Project monitoring should be conducted by the Department to ensure
compliance with policies and procedures, to ensure that funds were
used for the approved purpose, to determine whether the funded projects were successful and whether FTNOP met its overall objectives. Our review identified the following:
40 projects totalling $2.23 million in approved funding the
required audit and review process was not conducted for any
project. This process is intended to determine whether there was
compliance with policies and procedures and to determine
whether adequate documentation was available to support
payments.
11 projects totalling $434,585 in approved funding no site
visits were made.
40 projects totalling $2.23 million in approved funding the
Department did not provide a Terms of Reference for a Final
Report to any proponent as required. As a result, it is likely that
Final Reports from proponents will not be comparable or
include all information necessary for the Department to
determine whether the project was completed in accordance
with the approved projects objectives and costs.
10 projects with payments totalling $459,093 in approved
funding a written comprehensive final report was not
submitted within 30 days of the project completion date as
required.
7 projects totalling $405,719 in approved funding these
projects were not completed by the proponent as outlined in
their original submission. For example, in one instance the
proponent was paid $119,642 for 3 projects that were to
undertake a resource assessment of a fish species in certain
fishing zones. The Final Report identified a number of areas
where the actual project was different from the approved
project, including 20 sites done instead of 30 sites, 4 days of
data collection instead of 6 days and 34 days for surveying
instead of 50 days in one zone, 5 days of data collection instead
of 8 days and 8 survey days instead of 50 days in the other zone.
In addition, there was no evidence of a required power point
presentation, incorporation of other exploratory fisheries, and
feasibility of assessment of transmitter implants.
The Department did not identify performance indicators for each of its objectives or establish measurable targets for each of the performance indicators. As a result, it could not measure actual results against any targets to determine whether the FTNOPs objectives were being met.
Be the first one to leave a comment. (Click on the Post Comments link below, then use the form.)
|