Gander Airport Cold Storage and Live Seafood Holding Facility Nearing Completion

Gander Airport Cold Storage and Live Seafood Holding Facility Nearing Completion

Construction is nearing completion on a 27,000-square-foot cold storage and live seafood holding facility at the Gander International Airport in Central Newfoundland.

“We’re targeting substantial completion before Christmas and are confirming the final commissioning schedule,” said Tony Hiscock, vice president and CFO for the Gander International Airport Authority in September.

“The project is progressing, with 90 per cent exterior work complete and mechanical and electrical installation well underway. The rough-in is complete. We’re expecting the refrigerated panels later this month, which will allow us to finish the facility,” said Hiscock.

The cold storage facility will have 6,000 square feet of refrigerated space and 7,000 square feet for holding live lobster for export, complete with water treatment systems, seawater storage tanks and cold/chilled storage. It will store over 75 tonnes of fresh or live seafood.

“Meanwhile, we are working with airlines and producers to encourage quick adaptation and facility use when it opens,” said Hiscock. “The reaction has been great. We’re hearing from seafood exporters across Atlantic Canada, not just Newfoundland and Labrador. There’s optimism about the opportunities the facility will create. We’re working to match volumes and markets with available air cargo lift, and the opportunity extends beyond seafood to other products that could benefit from air cargo service. With trade patterns shifting and Canada looking to build closer trade ties with Europe, we see a real opportunity for Gander to play a larger role.”

Gander’s location in Central Newfoundland is the most direct access air route to markets in Europe and Asia.

Hiscock said construction has experienced some delays due to longer lead times for materials and equipment, particularly the refrigerated panels, which are needed to move the interior work ahead.

“Those are expected later this month and everything else is already on site, so we don’t anticipate tariffs causing any further bumps in the road. Most exterior work is complete, and mechanical and electrical work has continued in the meantime,” he said.

While a date for the facility to open has yet to be set, it will be up and running by next spring in time for the Newfoundland and Labrador lobster seasons, said Hiscock.

The $10-million project is backed by up to $4,581,265 in financial support through the federal government’s National Trade Corridors Fund, $2,290,633 from the Atlantic Fisheries Fund, $2 million from the Gander International Airport, $926,600 from the Atlantic Canada Opportunities Agency (ACOA) and $2.3 million from the Newfoundland and Labrador government.